A proven track record across wind farms, substations, overhead power lines, distillery infrastructure and major earthworks.

Selected transmission access projects

  • Beauly–Denny — 74 km
  • Inveraray–Crossaig — 72 km
  • Tomatin–Knocknagael — 28 km
  • Dounreay–Myster — 26 km
  • Bhlairidh–Beinneun — 23 km
  • Boat of Garten projects — 30 km

Over 250 km of selected transmission access works delivered across Scotland.

Spittal Substation

Earthworks and on-site processing delivered for major energy infrastructure.

75,000 m³

Soil

60,000 m³

Soft excavation

200,000 m³

Hard rock excavation

260,000 m³

On-site processing

The scale of the works required coordinated excavation, processing, movement and placement of material across the site.

Spittal Substation

Thurso South

A substantial earthworks package delivered beside an environmentally sensitive watercourse.

A 500-metre system of ponds, ditches and check dams was established early to manage surface water and protect tributaries of the River Thurso.

The river is designated as both a Site of Special Scientific Interest and a Special Area of Conservation. The water-management system remained effective through significant earthworks and wet winter conditions.

70,000 m³

Soft excavation

65,000 m³

Hard excavation

47,000 m³

Imported material

Thurso South

Mybster Substation

Experience managing peat, imported material and remote logistics.

26,000 m³

Peat

48,000 m³

Imported material

Planned movement and placement of material supported safe, controlled progress across the site.

Mybster Substation

Overton (Macallan) – Phase 4

Large-scale excavation, processing and placement supported by owned LEBHERD plant and experienced teams.

1.2 m³

Bulk excavation

390,000 m³

Fill to bunds

810,000 m³

Fill to platforms

The project required practical engineering solutions across remote, steep and environmentally sensitive terrain.

Overton (Macallan) - Phase 4

Beauly-Denny

One of Europe’s largest overhead transmission projects, extending more than 220 km and incorporating over 600 towers.

75,000 km+

Access track

9

Borrow pits

200,000 m³

Material processed

130

Piling platforms

400+

Crane access pads

61

Rock anchor sites

The project required practical engineering solutions across remote, steep and environmentally sensitive terrain.

Beauly-Denny

Recognised for delivery and leadership

Balfour Beatty’s Managing Director’s Subcontractor Excellence Award recognised performance across the UK and Ireland.

The Edward Mackay engineers and supervisors went the extra mile and proactively identified areas where additional fencing was required to protect the A9 during construction and use.

The additional access works reduced helicopter use, improved progress and enabled construction teams to reach some of the most challenging tower locations on the route.

Balfour Beatty project award statement